Understanding TGD-E: Acoustic Compliance for Residential Developments
What is TGD-E?
Technical Guidance Document E (TGD-E) sets out the requirements for sound insulation and acoustic performance in buildings in Ireland, supporting Part E of the Building Regulations.
It defines how buildings must be designed and constructed to:
- Limit sound transmission between dwellings
- Control impact noise from floors and stairs
- Manage reverberation in shared internal areas
TGD-E applies primarily to:
- New residential developments
- Apartment buildings and multi-unit schemes
- Material change of use to residential
- Certain extensions adjoining other dwellings.
For developers, design teams, and contractors, compliance with TGD-E is essential to achieve regulatory approval, avoid costly remedial works, and ensure occupant comfort.
Key Objectives of Part E of the Building Regulations
TGD-E supports two core regulatory requirements:
E1 – Sound Insulation
- Buildings must achieve reasonable resistance to airborne and impact sound transmission between adjoining dwellings or rooms.
- Applies to:
- Walls between dwellings
- Floors (including separating floors and stairs)
- Junctions and flanking paths
- Walls & Floors Between Dwellings and Other Space

E2 – Reverberation Control
- Internal common areas must be designed to limit reverberation and noise build-up that could affect adjacent dwellings.
The Core Acoustic Requirements
TGD-E focuses on three fundamental acoustic considerations:
1. Airborne Sound Insulation
This relates to noise transmitted through walls and floors, such as:
- Speech
- TV or music
- General living noise
Typical requirements include:
- ≥ 53 dB DnT,w between dwellings
2. Impact Sound Insulation
Impact noise occurs from physical contact with building elements, such as:
- Footsteps
- Dropped objects
- Furniture movement
Typical requirements include:
- ≤ 58 dB L’nT,w for floors
3. Reverberation in Common Areas
Common areas such as:
- Corridors
- Stairwells
- Entrance lobbies
must be designed to reduce echo and noise build-up through acoustic absorption treatments.
Structure of TGD-E (Understanding the Sections)
TGD-E is divided into clear sections that guide compliance from design through to completion:
Section 0 – General Guidance
- Definitions and scope
- Sound transmission mechanisms:
- Direct transmission
- Flanking transmission
- Design considerations (layout, services, junctions)
Section 1 – Performance Requirements
- Sets minimum acoustic targets
- Defines compliance routes:
- Robust construction details
- On-site testing
Section 2 – Testing and Verification
- Mandatory pre-completion sound testing
- Specifies:
- Number of tests required
- Testing standards (EN ISO methods)
- Reporting procedures
- Includes provisions for:
- Failed tests
- Remedial action
Section 3 – Separating Walls
- Acceptable wall constructions:
- Masonry
- Cavity walls
- Timber frame systems
- Key considerations:
- Mass and density
- Junction detailing
- Flanking control
Section 4 – Separating Floors
- Floor construction types:
- Concrete floors
- Timber floors
- Includes:
- Impact sound control
- Floor finishes and overlays
- Ceiling treatments
Additional Technical Elements
- Flanking transmission control (critical compliance risk)
- Construction detailing and workmanship
- Approved or “deemed-to-satisfy” solutions
Testing Requirements under TGD-E
All applicable residential developments must demonstrate compliance through:
- On-site acoustic testing prior to completion
- Testing of:
- Airborne sound insulation
- Impact sound insulation
- Representative sample testing across units
Why TGD-E Compliance Matters
Failure to properly address TGD-E can result in:
- Failed acoustic tests
- Delays in project completion and sign-off
- Costly remedial works
- Poor occupant experience
Conversely, good acoustic design delivers:
- High-quality living environments
- Reduced complaint risk
- Increased asset value and marketability
Wave Dynamics Approach to TGD-E Compliance
Wave Dynamics are highly experienced in delivering TGD-E compliant projects. Our consultants have delivered more than 60,000 residential units since 2015 when the regulations came in. Wave Dynamics have extensive experience in Value Engineering in residential having worked with our clients on VE to acheive the acoustic targets for our projects as cost efficient as possible.
At Wave Dynamics, we integrate TGD-E requirements into every stage of project delivery:
Design Stage
- Acoustic strategy aligned with TGD-E
- Junction and flanking risk assessments
- Coordination with architectural and M&E design
- Facade Acoustics.
Construction Stage
- Site inspections and compliance audits
- Contractor guidance on detailing
- Early identification of acoustic risks
Pre-Completion
- Independent acoustic testing
- Troubleshooting and remedial strategy if required
- Clear, defensible compliance reporting
Future Trends in Acoustic Compliance
While TGD-E sets the minimum standard, projects are increasingly targeting:
- Enhanced acoustic performance beyond compliance
- Alignment with:
- BS 8233
- BREEAM, LEED and WELL
- HPI (Home Performance Index)
This reflects growing expectations around wellbeing, ESG performance, and building quality.
Conclusion
Technical Guidance Document E is the cornerstone of acoustic compliance in Ireland, ensuring that residential buildings provide a reasonable standard of sound insulation and internal acoustic comfort.
However, achieving compliance goes far beyond meeting minimum values — it requires:
- Thoughtful design
- Robust detailing
- Quality construction
- Expert testing and verification
Wave Dynamics provides end-to-end acoustic consultancy to ensure your project achieves compliance efficiently, avoids risk, and delivers a high-quality acoustic environment.













Jon Maguire (BSc Hons MIOA) brings over 8 years of expertise in acoustic consultancy, specialising in environmental acoustics with a focus on 3D modelling, assessments, and detailed design for industrial, commercial, and energy projects. He has lead noise assessments for key clients while thriving in multidisciplinary environments. Jon’s diplomatic communication skills are ideal for stakeholder consultation.
Jack is a Field Engineer at Wave Dynamics, supporting the delivery of environmental monitoring and acoustic consultancy services through detailed on-site fieldwork. He has hands-on experience in noise monitoring, vibration monitoring, and dust monitoring across a variety of infrastructure, construction, and environmental projects. Jack is involved in the setup, operation, and maintenance of monitoring equipment, ensuring accurate data collection in line with relevant standards and project requirements. He works closely with consultants and project teams, providing reliable field support that underpins high-quality assessments and reporting.
Aidan is the Director for all U.K Operations and has worked in multiple industries including for clients in the UK and internationally operating in the residential, industry, healthcare, education, and construction sectors.